11.

A finishes 60% of a job in 12 working days. B then joins A, and they finish the remaining work in 4 working days. How long would B alone take for the whole job? Assume constant work rates.

Show answer
Explanation

1. Find A's rate and the later combined rate.

rA=0.6012=0.05,rA+B=0.404=0.10r_A=\frac{0.60}{12}=0.05,\qquad r_{A+B}=\frac{0.40}{4}=0.10

Both rates are measured in jobs per working day.

2. Isolate B's rate and calculate B's solo time.

rB=0.10−0.05=0.05,tB=10.05=20 daysr_B=0.10-0.05=0.05,\qquad t_B=\frac1{0.05}=\boxed{20\text{ days}}

Answer: D = 20 days.

12.

A completes three units of work for every two completed by B in the same time. Together they finish a job in 12 working days. How many working days would A alone take? Assume constant work rates.

Show answer
Explanation

1. Use the rate ratio of 3:2. A supplies three of the five parts of their combined daily output.

rA=35×112=120r_A=\frac35\times\frac1{12}=\frac1{20}

2. Convert A's daily rate to a completion time.

tA=11/20=20 dayst_A=\frac{1}{1/20}=\boxed{20\text{ days}}

Answer: A = 20 days.

13.

Team A works twice as fast as team B and would finish a job 18 working days sooner than B. How many working days would the two teams need together? Assume constant work rates.

Show answer
Explanation

1. Convert the rate relationship into a time relationship. If A takes t days, B takes 2t days.

2t−t=18⇒t=182t-t=18\quad\Rightarrow\quad t=18

Thus A takes 18 days and B takes 36 days.

2. Add their rates.

ttogether=11/18+1/36=11/12=12 dayst_{\text{together}}=\frac{1}{1/18+1/36} =\frac{1}{1/12}=\boxed{12\text{ days}}

Answer: C = 12 days.

14.

A and B together finish a job in 10 working days, B and C in 15, and A and C in 12. How many working days do all three together need? Assume constant work rates.

Show answer
Explanation

1. Add all three pair rates. This counts each team's rate twice.

2(rA+rB+rC)=110+115+112=6+4+560=142(r_A+r_B+r_C)=\frac1{10}+\frac1{15}+\frac1{12} =\frac{6+4+5}{60}=\frac14

2. Halve the sum and take its reciprocal.

rA+rB+rC=18,t=8 daysr_A+r_B+r_C=\frac18,\qquad t=\boxed{8\text{ days}}

Answer: D = 8 days.

15.

Machine A can process a batch in 6 hours. B and C together need 4 hours, while A and C together need 3 hours. How long would B alone take for the same batch? Assume constant work rates.

Show answer
Explanation

1. Isolate C's hourly rate.

rC=rA+C−rA=13−16=16r_C=r_{A+C}-r_A=\frac13-\frac16=\frac16

2. Subtract C's rate from B and C's combined rate.

rB=14−16=112⇒tB=12 hoursr_B=\frac14-\frac16=\frac1{12} \quad\Rightarrow\quad t_B=\boxed{12\text{ hours}}

Answer: B = 12 hours.