Time and Work

Practice problems involving work, efficiency, and time.

Formulas & shortcuts
31.

A needs 16 working days and B needs 24 to finish a job alone. A starts first and works until completion. B joins later and also works until completion. The job finishes 12 working days after A starts. After how many working days did B join? Assume constant work rates.

Show answer
Explanation

1. Find how much work B supplies. A works throughout the 12 days.

WB=1−1216=14W_B=1-\frac{12}{16}=\frac14

2. Calculate B's working time and starting delay.

tB=1/41/24=6 dayst_B=\frac{1/4}{1/24}=6\text{ days} Joining delay=12−6=6 days\text{Joining delay}=12-6=\boxed{6\text{ days}}

Answer: A = 6 days.

32.

A and B need 8 and 12 working days respectively to finish a job alone. They alternate 6-hour working days until it is complete. How much earlier is completion if A works the first day instead of B? Assume constant work rates.

Show answer
Explanation

1. Find the common position after eight days. In either order, four cycles complete:

4(18+112)=564\left(\frac18+\frac1{12}\right)=\frac56

2. Compare the final two turns.

With A first, A works on day 9, leaving:

1−56−18=1241-\frac56-\frac18=\frac1{24}

B needs three hours on day 10, since B's hourly rate is 1/72.

With B first, B works on day 9, leaving:

1−56−112=1121-\frac56-\frac1{12}=\frac1{12}

A needs four hours on day 10, since A's hourly rate is 1/48.

3. Compare completion times. Starting with A finishes one working hour earlier.

Answer: C = 1 working hour.

33.

A and B together finish a job in 12 working days, B and C in 15, and A and C in 20. All three work together for 5 days; then B and C leave. How many additional working days does A need? Assume constant work rates.

Show answer
Explanation

1. Find the total rate from the three pair rates.

rA+B+C=12(112+115+120)=110r_{A+B+C}=\frac12\left(\frac1{12}+\frac1{15}+\frac1{20}\right) =\frac1{10}

2. Find the remaining work and A's individual rate.

Wleft=1−510=12,rA=110−115=130W_{\text{left}}=1-\frac5{10}=\frac12,\qquad r_A=\frac1{10}-\frac1{15}=\frac1{30}

3. Calculate A's additional time.

t=1/21/30=15 dayst=\frac{1/2}{1/30}=\boxed{15\text{ days}}

Answer: B = 15 days.

34.

Three printers can each print an entire 7200-label order in 4, 6 and 12 hours respectively. All start at 9:00 a.m. on separate portions. The fastest printer stops at 10:00 a.m.; the others continue without breaks. At what time is the order finished? Assume constant work rates.

Show answer
Explanation

1. Calculate the fraction printed during the first hour.

W=14+16+112=12W=\frac14+\frac16+\frac1{12}=\frac12

2. Find the rate of the two remaining printers.

r=16+112=14r=\frac16+\frac1{12}=\frac14

They need:

textra=1/21/4=2 hourst_{\text{extra}}=\frac{1/2}{1/4}=2\text{ hours}

Two hours after 10:00 a.m. is 12:00 noon.

Answer: D = 12:00 noon.