21.

A conveyor adds material to an initially empty storage bay at a rate that would fill it in 8 hours. A second conveyor removes material at a rate that would empty a full bay in 24 hours. Both run together, with the removal conveyor taking material as it arrives. How long until the bay is full? Assume constant work rates.

Show answer
Explanation

1. Subtract the removal rate from the filling rate.

rnet=18−124=3−124=112r_{\text{net}}=\frac18-\frac1{24} =\frac{3-1}{24}=\frac1{12}

2. Divide one bay by the net accumulation rate.

t=11/12=12 hourst=\frac{1}{1/12}=\boxed{12\text{ hours}}

The net rate is positive, so the bay eventually fills.

Answer: D = 12 hours.

22.

A takes twice as long as B and four times as long as C to complete a job alone. Together they finish in 4 working days. How many working days would B alone take? Assume constant work rates.

Show answer
Explanation

1. Express the three solo times. If A takes x days, B takes x/2 and C takes x/4.

1x+2x+4x=14\frac1x+\frac2x+\frac4x=\frac14

2. Solve for x, then select B's time.

7x=14⇒x=28,tB=282=14 days\frac7x=\frac14\quad\Rightarrow\quad x=28,\qquad t_B=\frac{28}{2}=\boxed{14\text{ days}}

Answer: C = 14 days.

23.

Six identical type-P machines process a batch in 10 hours. Eight identical type-Q machines process the same batch in 15 hours. What is the output-rate ratio of one P machine to one Q machine? Assume constant work rates.

Show answer
Explanation

1. Find the rate of one machine of each type.

rP=16×10=160,rQ=18×15=1120r_P=\frac1{6\times10}=\frac1{60},\qquad r_Q=\frac1{8\times15}=\frac1{120}

2. Form the requested P-to-Q rate ratio.

rP:rQ=160:1120=2:1r_P:r_Q=\frac1{60}:\frac1{120}=\boxed{2:1}

Answer: B = 2:1.

24.

A and B need 10 and 15 working days respectively to finish a job alone. They work on alternate days, A on day 1 and B on day 2, repeating this order. Each working day is 6 hours. When is the job completed? Assume constant work rates.

Show answer
Explanation

1. Calculate work per two-day cycle.

Wcycle=110+115=16W_{\text{cycle}}=\frac1{10}+\frac1{15}=\frac16

Five cycles complete five-sixths of the job in ten days.

2. Check the final individual turns.

Wleft after day 11=1−56−110=115W_{\text{left after day 11}} =1-\frac56-\frac1{10}=\frac1{15}

B completes exactly this fraction during the full six-hour day 12. The job finishes at the end of day 12.

Answer: A = At the end of day 12.

25.

A can complete a job in 18 working days, B in 36 and C in 36. A works every day; B and C assist only on days 3, 6, 9 and so on. What is the total number of working days needed? Assume constant work rates.

Show answer
Explanation

1. Calculate a three-day cycle. A works all three days, while B and C each work once.

Wcycle=318+136+136=29W_{\text{cycle}}=\frac3{18}+\frac1{36}+\frac1{36}=\frac29

2. Check the remainder after four cycles.

Wleft=1−4×29=19W_{\text{left}}=1-4\times\frac29=\frac19

A completes this alone in:

textra=1/91/18=2 dayst_{\text{extra}}=\frac{1/9}{1/18}=2\text{ days}

Total time is 14 working days. The job finishes before the next assistance day.

Answer: C = 14 days.