A conveyor adds material to an initially empty storage bay at a rate that would fill it in 8 hours. A second conveyor removes material at a rate that would empty a full bay in 24 hours. Both run together, with the removal conveyor taking material as it arrives. How long until the bay is full? Assume constant work rates.
Show answer
1. Subtract the removal rate from the filling rate.
2. Divide one bay by the net accumulation rate.
The net rate is positive, so the bay eventually fills.
Answer: D = 12 hours.