Here “chain rule” means compound proportion in arithmetic: combine direct and inverse effects one factor at a time.
- W
- Work output.
- N
- number of workers.
- D
- working days.
- H
- Working hours per day.
- e
- output per worker-hour.
Production model
Independent workers, constant rate, divisible work.
Find required days
More output needs more days; more capacity needs fewer.
Find required workers
Round upward if a whole number must meet a deadline.
Compare output
Use when the production assumptions hold.
Person-days of supplies
Fixed stock and unchanged consumption per person per day.
Direct versus inverse
Decide the effect on the unknown while holding other factors fixed.
Explanations and worked examples
Open a method when you need more detail.
Full notation guide
- W
- Work output.
- N
- number of workers.
- D
- working days.
- H
- Working hours per day.
- e
- output per worker-hour.
- Subscripts 1 and 2
- Original and new scenarios respectively.
- k
- Constant of proportionality for the stated model.
1. Decide which factors are direct and which are inverse
Identify the unknown first. Ask what happens to it when one factor increases and everything else stays fixed. For required time, more work is direct; more workers, hours or productivity are inverse.
Worked example
Five identical machines make 600 parts in a fixed shift. How many parts do eight machines make in the same shift?
- Output is directly proportional to machine count.
- New output = 600 × 8/5 = 960.
960 parts.
Remember
- This is compound proportion, not the differentiation chain rule from calculus. Proportionality must be supported by the problem.
2. Combine workload, workforce and daily hours
Start from W = NDHe, then divide the equation for the new case by the original. Solving for days gives one direct factor for work and inverse factors for capacity.
Worked example
12 workers working 6 hours daily complete a job in 10 days. How many days do 15 equally efficient workers working 8 hours daily need for twice the work?
- Work factor = 2; worker factor = 12/15; hours factor = 6/8.
- Days = 10 × 2 × 12/15 × 6/8 = 12.
12 days.
Remember
- Keep hours per day separate from total hours. Greater output does not necessarily mean greater time if capacity also changes.
3. Calculate a workforce and round only at the end
Required worker count is proportional to work and inversely proportional to available days, daily hours and per-worker productivity. If workers must be whole people, a fractional requirement must be rounded up to meet a strict deadline.
Worked example
Eight workers finish a job in 15 days. At unchanged hours and efficiency, how many workers are needed to finish in 7 days?
- Required count = 8 × 15/7 = 120/7 ≈ 17.14.
- 17 workers provide only 119 worker-days; the job needs 120.
- Round up to 18 workers.
18 workers.
Remember
- Do not round intermediate factors. Rounding up assumes the question permits adding whole workers and that additional workers remain productive.
4. Include efficiency without double-counting it
Efficiency e is output per worker-hour. An increase of p% multiplies e by 1 + p/100. Treat this as a separate factor only if it has not already been included in the stated output rate.
Worked example
10 workers make 400 units in a day. For the same hours, 12 workers each become 25% more productive. Find daily output.
- Worker factor = 12/10.
- Productivity factor = 1.25.
- Output = 400 × 12/10 × 1.25 = 600.
600 units.
Remember
- If a machine or material bottleneck limits output, proportional scaling with workers may fail.
5. Use person-days for fixed supplies
With equal fixed consumption per person per day, stock can be expressed as person-days. After some days have passed, subtract consumed stock before changing the population.
Worked example
Food for 30 people lasts 20 days. After 5 days, 15 more people join. How many additional days will the remaining food last?
- Initial stock = 30 × 20 = 600 person-days.
- Consumed = 30 × 5 = 150; remaining = 450.
- New population = 45; duration = 450/45 = 10 days.
10 additional days; 15 days from the start.
Remember
- Assume no spoilage, new supplies or change in individual consumption. Do not apply the original 20 days to the remaining stock.
6. Measure the workload correctly
The relevant work measure may be area or volume, not merely one length. Painting comparable surfaces scales with area; excavating comparable material scales with volume. Then apply the worker-time model.
Worked example
Six workers excavate a 10 m × 2 m × 1 m trench in 4 days. At the same efficiency and hours, how long do eight workers need for a 15 m × 2 m × 2 m trench?
- Old volume = 20 m³; new volume = 60 m³.
- Work factor = 60/20 = 3.
- Days = 4 × 3 × 6/8 = 9.
9 days.
Remember
- Assume comparable soil and access. Doubling a dimension does not necessarily double the entire workload when other dimensions also change.